Example Scrum Certification Test Questions from International Scrum Institute

Check out your Example Scrum Certification Test Questions which are very similar to the Test Questions of your Scrum Master Accredited Certification™, Scrum Product Owner Accredited Certification™, Scrum Team Member Accredited Certification™, Scrum Coach Accredited Certification™, Scrum Trainer Accredited Certification™, Scaled Scrum Expert Accredited Certification™, Scrum Certification for Java Developer™, Scrum Certification for Web Developer™ and Scrum Certification for Mobile App Developer™ Programs.
Once you study questions and answers for your Scrum Certification Program you would love to pursue, you can feel absolutely confident to pass your Scrum Certification exam.


Question 1
What kind of software development projects can be executed by Scrum Project Management Framework?
  • Choice-1: Complete software packages
  • Choice-2: Customer projects
  • Choice-3: Sub-systems, components or parts of bigger systems
  • Choice-4: All kinds of software development projects
  • Choice-5: None of the given answers
Correct Answer: Choice-4 / All kinds of software development projects


Question 2
What does NOT belong to cornerstones of the agile manifesto?
  • Choice-1: Individuals and interactions over processes and tools
  • Choice-2: Working software over comprehensive documentation
  • Choice-3: Processes over people
  • Choice-4: Customer collaboration over contract negotiation
  • Choice-5: Responding to change over following a plan
Correct Answer: Choice-3 / Processes over people


Question 3
What is defined by the Scrum Framework?
A) Rules & Roles
B) Document guidelines
C) Artifacts and events
  • Choice-1: A
  • Choice-2: B
  • Choice-3: C
  • Choice-4: A, B ,C
  • Choice-5: A, C
Correct Answer: Choice-5 / A, C


Question 4
Where are the customer requirements stored?
  • Choice-1: In the Product Backlog
  • Choice-2: In the Sprint Backlog
  • Choice-3: In a database
  • Choice-4: In a Scrum Product Requirement Specification
  • Choice-5: Nowhere. The Scrum Product Owner knows them
Correct Answer: Choice-1 / In the Product Backlog


Question 5
Which ones of the following main roles are defined by Scrum Framework?
A) Scrum Tester
B) The Scrum Team
C) Scrum Manager
D) Scrum Master
E) Scrum Product Owner
  • Choice-1: A, B, C, D, E
  • Choice-2: B, C, D, E
  • Choice-3: B, D, E
  • Choice-4: A, B, D, E
  • Choice-5: A, B, C, D
Correct Answer: Choice-3 / B, D, E


Question 6
Which ones of the following main events are defined by Scrum Framework?
A) Sprint Planning Meeting
B) Sprint Retrospective Meeting
C) Sprint Review Meeting
D) Mid-Sprint Status Review Meeting
E) Daily Scrum Meeting
  • Choice-1: A, B, C, D, E
  • Choice-2: A, B, C, D
  • Choice-3: A, C, D, E
  • Choice-4: A, B, C, E
  • Choice-5: A, C, E
Correct Answer: Choice-4 / A, B, C, E


Question 7
Which concept is NOT defined in the Scrum Framework?
  • Choice-1: Scrum Master
  • Choice-2: Project Manager
  • Choice-3: Scrum Product Owner
  • Choice-4: Daily Scrum
  • Choice-5: Scrum Product Burndown
Correct Answer: Choice-2 / Project Manager


Question 8
What is important in all Scrum projects?
A) Self-organization
B) Clear hierarchies in the company
C) Communication
D) Continuous improvement
  • Choice-1: A, B, C, D
  • Choice-2: A, C, D
  • Choice-3: A, D
  • Choice-4: A
  • Choice-5: A, B
Correct Answer: Choice-2 / A, C, D


Question 9
In software engineering what are the disadvantages of the classical waterfall model?
A) End-Product has to be fully anticipated beforehand.
B) Some requirements are implemented as defined in the beginning of the project, and yet they are not really needed by the customer.
C) Each phase is strictly separated.
  • Choice-1: A
  • Choice-2: B
  • Choice-3: C
  • Choice-4: A, B
  • Choice-5: A, B, C
Correct Answer: Choice-5 / A, B, C


Question 10
What are the advantages of the Scrum Framework?
  • Choice-1: Fine-grained requirements are only defined when they are really needed.
  • Choice-2: All activities to design, build and test a certain functionality are kept together in one phase.
  • Choice-3: Changes are expected and welcomed by Scrum team.
  • Choice-4: All of the given answers
  • Choice-5: None of the given answers
Correct Answer: Choice-4 / All of the given answers